Project: Hoton 2 Field Development
Location: UK Southern North Sea
Client: BP
Core Service: Concept Study
Key Activity: Pipelines and Umbilicals
Duration: 2 Months
Hoton Platform
New 8" Riser Routing
Pressure Flask Lifting Study
3 - 3
<
>
The Hoton field is located in the Southern sector of the North Sea. The field comprises a single production well mounted on a monopod type platform. Gas is exported via an 8” pipeline to the West Sole field with power and control via an electrohydraulic umbilical from West Sole.
The Client wished to drill a second well from the existing platform and required appraisal of options and costs for two pipelines to meet two differing production profiles.
The CWS scope included conceptual sizing of two pipelines, screening of pipeline route options, and estimation of material, fabrication and installation costs for the two pipeline size options and one umbilical option.
Project: Hoton 2 Field Development
Location: UK Southern North Sea
Client: BP
Core Service: Concept Study
Key Activity: Pipelines and Umbilicals
Duration: 2 Months
The Hoton field is located in the Southern sector of the North Sea. The field comprises a single production well mounted on a monopod type platform. Gas is exported via an 8” pipeline to the West Sole field with power and control via an electrohydraulic umbilical from West Sole.
The Client wished to drill a second well from the existing platform and required appraisal of options and costs for two pipelines to meet two differing production profiles.
The CWS scope included conceptual sizing of two pipelines, screening of pipeline route options, and estimation of material, fabrication and installation costs for the two pipeline size options and one umbilical option.