Project: Broom Pipeline Investigation and Recovery
Location: UK North Sea
Client: Petrofac Facilities Management (PFM)
Core Service: Pipeline Failure Investigation
Key Activity: Operational Support
Duration: 12 Months
Working subsea
Model of Broom Pipeline Insulation Clam Shells
Model of Broom Pipeline Jointing Detail
3 - 3
<
>
The Broom field is located in the East Shetland basin approximately 7km SW of the Heather platform in 140m of water. Following the detection of low fluid arrival temperatures in 2008, PFM engaged Clear Well Subsea to investigate probable causes and provided operations support for the investigation phase.
A detailed review of the Broom pipelines was carried out which identified two potential failure causes. Following the preliminary evaluation work, bundle stabilisation and intelligent pigging operations were carried out which conclusively identified the pipeline failure mode and allowed analysis of the probable causes. This information was used as a basis for the replacement pipeline project which commenced in mid 2009.
Initial investigation and evaluation, development of detailed pigging and stabilisation programmes, operational support onshore and offshore for the intelligent pigging programme, operational support onshore and offshore for the pipeline cleaning programme and development of preliminary pipeline design, routing and costs for the replacement pipeline.
Project: Broom Pipeline Investigation and Recovery
Location: UK North Sea
Client: Petrofac Facilities Management (PFM)
Core Service: Pipeline Failure Investigation
Key Activity: Operational Support
Duration: 12 Months
The Broom field is located in the East Shetland basin approximately 7km SW of the Heather platform in 140m of water. Following the detection of low fluid arrival temperatures in 2008, PFM engaged Clear Well Subsea to investigate probable causes and provided operations support for the investigation phase.
A detailed review of the Broom pipelines was carried out which identified two potential failure causes. Following the preliminary evaluation work, bundle stabilisation and intelligent pigging operations were carried out which conclusively identified the pipeline failure mode and allowed analysis of the probable causes. This information was used as a basis for the replacement pipeline project which commenced in mid 2009.
Initial investigation and evaluation, development of detailed pigging and stabilisation programmes, operational support onshore and offshore for the intelligent pigging programme, operational support onshore and offshore for the pipeline cleaning programme and development of preliminary pipeline design, routing and costs for the replacement pipeline.